The government needs to invest in tourism and fishing activities near the dam Kampala, Uganda | ISAAC KHISA | Returning to Kayunga District after nearly a decade of absence, one could easily be astonished with the rapid transformations. The once dusty and potholed roads as well as the run-down structures …
Read More »Unconsumed power will hit the budget hard – Muhakanizi
Kampala, Uganda | THE INDEPENDENT | Uganda must now reserve money to pay for generated but unconsumed power for the next five years, The Secretary to the Treasury Keith Muhakanizi has said. Muhakanizi told diplomats and economists at an IMF organised meeting at Sheraton Kampala on Monday evening that Uganda – …
Read More »Former workers seek compensation for injuries sustained at Isimba dam
Kampala, Uganda | THE INDEPENDENT | Kayunga district authorities have petitioned China International Water & Electric Corporation-CWE, the contractor that undertook the construction of Isimba Hydropower Project to increase compensation for workers injured at the site during the construction. Construction of the 183 Megawatt power plant, the 3rd largest in …
Read More »Museveni hails China for funding Isimba dam construction
Kampala, Uganda | THE INDEPENDENT | President, Yoweri Museveni commissioned Isimba dam in Kayunga district. Museveni switched on four turbines of the 183MWs dam amidst cheers from high profile dignitaries who accompanied him. Construction of the dam took 47 months and cost US$ 566 million. 85% of the money was …
Read More »UEGCL saga: Muhakanizi audit blocked
Details of accusations against Isabalija emerge In what appears to be a continuing standoff between the Secretary to Treasury (ST), Keith Muhakanizi and officials of the Uganda Electricity Generation Company Ltd (UEGCL), The Independent has learnt that Muhakanizi was apparently blocked from auditing UEGCL accounts. The Independent has obtained a …
Read More »UEGCL visits Isimba, warns on crack repairs
The Board of Directors of Uganda Electricity Generation Company Limited (UEGCL) has warned about none conformity to agreed repair methods for previously observed cracks at the Isimba Hydro Power Project. The board made the observation Friday when they visited the Isimba Hydro Power Project site to assess the progress of the …
Read More »VIDEO: UEGCL faults Isimba Dam constractors
NBS: Officials from the Uganda Electricity Generation Company would leave nothing to chance during an inspection of the Isimba dam in Kamuli. The officials who put the contractors on the spot over shoddy construction work, where quick to whip out the contract and read it out when the contractors attempted …
Read More »
The Independent Uganda: You get the Truth we Pay the Price