The government needs to invest in tourism and fishing activities near the dam Kampala, Uganda | ISAAC KHISA | Returning to Kayunga District after nearly a decade of absence, one could easily be astonished with the rapid transformations. The once dusty and potholed roads as well as the run-down structures …
Read More »Why Karuma Dam commissioning has been extended again
Contractor, Ministry of Energy say it will be ready in November 2020 Kampala, Uganda | JULIUS BUSINGE | The commissioning of the 600MW Karuma Hydropower Dam has again been extended to November 2020 to allow the contractor deliver a fit for purpose project. This is the third time that Karuma …
Read More »Uganda Electricity Generation Company sees profit growth
Isimba and Karuma power stations are expected to boost its earnings Kampala, Uganda | JULIUS BUSINGE | Officials at Uganda Electricity Generation Company Limited (UEGCL) are hoping to record improved performance after posting the first net profit in 18 years. The company reported at the end of last year that …
Read More »Rolling out power grids across Africa
Uganda ranked among worst performers as progress stalls on continent | THE INDEPENDENT | Uganda has been ranked among the four countries with the lowest electricity connections in Africa which is the darkest continent in the world. According to an analysis by Carolyn Logan, the Deputy Director of the research …
Read More »Electricity generation company in record Shs24bn profit
Kampala, Uganda | JULIUS BUSINGE | Uganda Electricity Generation Company Limited (UEGCL) announced on Dec.17 that it had made a net profit of Shs24.7bn for the financial year 2018/19, up from a loss of Shs10.8bn a year before. Officials said the profit, the first since the company’s inception in 2001, …
Read More »We will use our staff to maintain power dams -UEGCL
The Uganda Electricity Generation Company Limited in partnership with government and development partners is working to train all its 100 staff in the Operation and Maintenance Unit to be able to run the power dams. Kampala, Uganda | JULIUS BUSINGE | These dams in question include; the newly commissioned 183MW …
Read More »Uganda joins international body on power dams
There is good news for Uganda which is investing heavily in the energy sector development projects to support economic activities. | THE INDEPENDENT | On June 14, Uganda was formally elected as the 101 member of the International Commission on Large Dams (ICOLD). This was announced at the ICOLD’s 87th …
Read More »Construction of Ayago hydro power still hangs in balance
Kampala, Uganda | THE INDEPENDENT | The construction of the 840 Mega Watts Hydroelectric Power Plant on Victoria Nile in Ayaygo in Nwoya district still hangs in balance. Government signed an agreement with Mapa, a Turkish Construction firm to construct the dam in 2013 at the tune of US $1.970 …
Read More »$567million Isimba dam switched on
Private sector players ask for affordable electricity to power industries Kampala, Uganda | JULIUS BUSINGE | On March 21, President Yoweri Museveni commissioned the Isimba Hydropower Dam, adding 183MW to the national grid. But the private sector, who consume most of the electricity accounting for 20% of their production …
Read More »Mutebile, Kasekende, Muhakanizi set to leave
MUTEBILE: What happens next? Kampala, Uganda | HAGGAI MATSIKO | Anxiety is building about what the future holds for management of Uganda’s economy as the curtain slowly comes down on three prominent figures; Bank of Uganda Governor Tumusiime Mutebile, his deputy Louis Kasekende at Bank of Uganda, Secretary to the Treasury …
Read More »